Moscow, Krasnopresnenskaya embankment, 14. Ground anchors: 219 pcs. · 6,800 m
Moscow, st. Sergeya Makeeva, 7. Ground anchors: 769 pcs. · 10,407 m. Waler beam: 700 m
village Shchapovskoe, Moscow. Ground anchors: 78 pcs. · 1,380 m. Engineering and road infrastructure of the food and construction clusters in the settlement of Shchapovskoye (New Moscow): two water intake units with a looped water supply network, a sewage pumping station and a treatment facility with a sewer line, local treatment facilities with a supply collector, construction and reconstruction of sections of the road network.
Moscow, st. Tushinskaya, vl. 24. Ground anchors: 642 pcs. · 15,042 m. Cementation of soils at the base of the BPS: 6,018 m. Jet grouting: 3 333 m
Moscow, st. Presnensky Val, s/u 27/5. Cementation of soils at the base of the BPS: 496 m