Request a quote

Tube-à-manchette grouting

Interval injection of solution into the soil through a pipe with cuffs that open only at a given pressure. You can re-treat the interval, control the area where the solution spreads and prevent it from reaching the surface.

View interactive diagram →
01

Where it is used

  • — Strengthening the foundations of existing buildings
  • — Cramped construction conditions
  • — Emergency leaks and quicksand
  • — Waterproofing, problematic soils
02

Specifications

Wells
Ø 40–100 mm
Cuff pitch
0.3–0.5 m
Discharge pressure
0.3–5 MPa
Crude plugging
hardens in 1–3 days
Durability gain
setting 2–3 days, design ≈ 28 days
03

Work sequence

  1. 01 Well drilling; in loose soils - with casing pipes
  2. 02 Installation of a collar column and plugging of the annulus
  3. 03 Bottom-up injection with a double-sleeve packer until “failure” or design volume
  4. 04 Hardening: zones of adjacent intervals close into a single massif
04

Standards and regulations

  • — SP 291.1325800.2017 “Soil-cement reinforced structures”
  • — SP 22.13330 “Foundations of buildings and structures”
  • — SP 45.13330 “Earth structures, foundations and foundations”
  • — GOST R 59538-2021, GOST R 70696-2023 - cement-based injection mortars
  • — GOST 31108-2016 “General construction cements”
  • — GOST 23732 - water for concrete and mortars
  • — STO NOSTROY 2.3.18-2011 - soil strengthening using injection methods

We'll select the technology for your project